T.C.O. requirements include but not limited to:
1) All life safety related permits and sub permits closed including the public safety radio booster if required, associated Right of Way work, any fire suppression system or smoke control system;
2) Outside agency certification approvals complete and City approved (Broward County, F.D.O.T., Florida State, etc);
3) Planning and Zoning approvals complete with Commission requirements met;
4) Building systems (structural, electrical, plumbing, mechanical) almost 100% complete and City inspected;
5) Threshold and special inspector sign off letters City approved;
6) Final termite certificate City approved;
7) Final survey and elevation certificate City approved;
8) Flood and/or FEMA/CCCL requirements met (flood resistant construction in place and inspected; certification of breakaway construction by the designer of record City approved, etc);
9) Hurricane protection in place and inspected;
10) Site work complete and handicap accessible;
11) Payment of any required fees (Fire Assessment Fees, all required permits paid for, etc);
12) Any required easements or ROW dedications completed and recorded.
13) Release of lien, warranty and maintenance bond for public improvements.
14) Green Building Certification if required compliance must be up to date
15) BDA System must be 100% completed and inspected.